How long does it take?

This depends on whether we look to develop a single Feed-in Tariff turbine or larger Renewable Obligation Certifcate (ROC) scheme on your land.

Once you have provided us with a map of your landholdings using the Land Assessment Tool, we will get back to you within a matter of days with our initial feasibility assessment. If the scheme is worth pursuing we will provide you with a valuation of how much you could earn and look to agree terms to lease your land. Subject to the agreed terms, Infinergy will look to cover the legal costs of completing these documents.

FiT Projects – Development of a typical single turbine

  • Initial Feasibility – 1 week
  • Agree Commercial Terms and complete legal agreements - 3 to 4 months
  • Commence on-site studies and prepare planning submission - 3 to 4 months
  • Local Planning Authority determination period – 4 months
  • Finance and construction preparation - 6 months
  • Construction and commissioning of the turbine - 9 months

ROC Projects – Development of a typical larger multi turbine wind farm

  • Initial Feasibility – 1 month
  • Agree Commercial Terms and complete legal agreements - 6 months
  • Commence on-site studies and prepare planning submission – 18 to 24 months
  • Local Planning Authority determination period – 4 months
  • Finance and construction preparation - 9 months
  • Construction and commissioning of the turbine – 12 to 18 months